Rourkela–Bondamunda 5th Line (BG): Pile Load Testing

Railway, Testing Projects · Rourkela, Odisha · 2026 · Client: South Eastern Railway

ND Infra is carrying out pile load tests for the construction of the 5th broad gauge (BG) line between Rourkela and Bondamunda on South Eastern Railway. We work for the contractor M/s Cimek Infra. Load testing checks that the piles carrying the new line's structures meet their design capacity before construction continues. A team of 35+ people is on this assignment, which is planned to take about 8 months.

Rourkela–Bondamunda 5th Line (BG): Pile Load TestingRourkela–Bondamunda 5th Line (BG): Pile Load TestingRourkela–Bondamunda 5th Line (BG): Pile Load Testing

Key features

  • Pile load testing on a broad gauge railway line project
  • Checks piles against their design capacity before structures are built on them
  • Work alongside a busy South Eastern Railway section

Project details

  • Duration: 8 months
  • Team on site: 35+
  • Scope: Pile load test
  • Main contractor: M/s Cimek Infra

Back to all projects · Discuss a similar project